Project Timeline / Milestone

PRJ-001 — Implementasi Infrastruktur IT
# Milestone Rencana Realisasi Status Bobot Progress Action
1
Persiapan Project
MILE-001
Persiapan
01-10-2026
s/d 02-10-2026
01-10-2026
s/d 01-10-2026
Completed
10.00%
Progress 100%
Edit
2
Pengadaan Material
MILE-002
PENGADAAN
02-10-2026
s/d 04-10-2026
02-10-2026
s/d 15-10-2026
Completed
30.00%
Progress 100%
Edit
3
Instalasi Infrastruktur
MILE-003
Instalasi
05-10-2026
s/d 08-10-2026
-
s/d -
Completed
45.00%
Progress 100%
Edit
4
Testing & Serah Terima
MILE-004
Testing & Serah Terima
09-10-2026
s/d 10-10-2026
09-10-2026
s/d 15-10-2026
Completed
15.00%
Progress 100%
Edit